• Project Code :  ERGP202200861
    • Project Description : REHABILITATION AND ASPHALTING OF AGRIC FARM ROAD AT BAGWA ANI OGBALIGBO NSUKKA WEST, PHASE 2.
  • Project Budget : N85,000,000 [ Eighty Five Million Naira ]

Nsukka/Udi Shadow Budget Group were those to track this project. This project was tracked jointly by Udi and Nsukka Shadow Budget Groups on Thursday 16th March 2023.

This project was tracked jointly by Udi and Nsukka Shadow Budget Groups on Thursday 16th March, 2023. It was observed that the road has been regraded, like; two weeks ago. However, there was no project’s signage and labelling to know which agency is doing this and if exactly the execution is appropriated project with code: ERGP202200861 , which is the exact location. May be, further follow up is needed by the community or @NDEBUMOGHQ to factualize the executor.